Experimental Results And Plan For The Optimisation Of The ITER Neutral Beam Injector Prototypes
Abstract
Data di Pubblicazione:
2023
Abstract:
To reach fusion conditions and control plasma configurations, two heating and current-drive neutral beam
injectors (NBIs) will provide the ITER plasma with 17MW each, by accelerating negative hydrogen/deuterium
ions. The challenging requirements of ITER NBIs (40A/1MeV D- for <=1 hour; 46A/870keV H- for <=1000s;
divergence <7mrad; aiming <2mrad) have never been simultaneously attained [1]. So, in the dedicated Neutral
Beam Test Facility (NBTF) at Consorzio RFX (Italy), an extended R&D activity aims at reaching full
performances and optimising reliable operation. To comply with the tight ITER schedule, the NBTF hosts
MITICA, full-scale ITER NBI prototype, and SPIDER, full-scale prototype of the NBI source with 100keV
particle energy [2]. SPIDER is dedicated to early investigation of negative ion production and extraction, source
uniformity, negative ion current density, beam optics. MITICA will focus on beam acceleration, in terms of optics
and high-voltage holding in vacuum, and on beam propagation, governed by neutralisation and electrostatic
removal of residual ions.
This contribution describes the rationale of the experimental plan and results of the NBTF devices. First a
summary of the scientific results in SPIDER will be provided, which confirm the findings of other RF sources
[3]; together with numerical modelling, they suggest that the plasma density shall be increased via improved
plasma confinement. Permanent magnets will be installed around the plasma source during the present SPIDER
shutdown to increase the plasma confinement; other improvements include replacement of the RF generators and
expansion of the pumping system. Regarding MITICA, a brief account of the voltage holding tests already
performed is given together with the solutions that are being implemented to address some of the issues. To
accelerate the attainment of the ITER NBI requirements, the planning of the next activities at the NBTF involves
also a smaller facility to test the effect of the permanent magnets.